Development Project - Code S
Excerpts from Weekly Report
Friday | Nov.
30, 2001
The Advanced Camera for Surveys (ACS) arrived at KSC.
The
Crew Aids and Tools (CATs) were received at KSC.
The
SAC and Multi-Use Lightweight Equipment (MULE) post shipment
CPTs were successfully completed.
Near
Infrared Camera and Multi-Object Spectrometer (NICMOS) Cooling
System (NCS)/Aft Shroud Cooling System (ASCS) Integration
of the relay box controllers into the Electronic Support Module
(ESM) has been completed. Regression testing (vibration and
Thermal Vacuum [TV]) was complete.
The sixth HST Crew Fam was successfully completed. All seven
crewmembers participated.
Kennedy
Space Center Vehicle: Columbia/OV-102
Shuttle & Payload Processing Status Report
Tuesday | Nov.
20, 2001
Columbia is in the Orbiter Processing Facility (OPF) undergoing
pre-launch processing for the Hubble Space Telescope servicing
mission. Airlock verification and Auxiliary Power Unit (APU)
leak and functional testing are continuing, and preparations
are under way to install the Main Engine heat shields.
|
|
|
|
|