NASA Logo, National Aeronautics and Space Administration

National Aeronautics and Space Administration

Goddard Space Flight Center

Astrophysics Science Division | Sciences and Exploration

This website is kept for archival purposes only and is no longer updated.

Skip Navigation
  :::
>
Mission Critical Multi-Media Gallery Hubble News Mission Updates Launch Info

  Mission Updates :: February Week 2

Home
Mission Updates
Mission Chronicles
Where Is Hubble Now?
Read how the mission unfolds week by week, day by day,
as the date of the shuttle launch approaches.

Kennedy Space Center
Vehicle: Columbia/OV-102
Shuttle Processing Status Report


Thursday | Feb. 14, 2002

The Shuttle Management Team is participating in the Flight Readiness Review today to assess the status of Shuttle Columbia's STS-109 Mission, currently scheduled for Feb. 28.

At Pad A, the Rotating Service Structure was moved to the parked position to prepare for the Auxiliary Power Unit (APU) hot fire later today.

The Hubble payload will be delivered to the pad early tomorrow and the Reaction Wheel Assembly will be replaced with a new unit before the payload is installed aboard Columbia on Sunday. CLICK HERE FOR MORE IMAGES...

A Risk Assessment Team is continuing its investigation to determine the stress integrity of the bolts that attach the hydraulic pumps to the three APUs.

Monday | Feb. 11, 2002
Shuttle Columbia remains on schedule for the planned liftoff of the Hubble Servicing Mission at 6:48 a.m. EST on Feb. 28. At Pad A, the launch team opted to complete hypergolic fueling on Saturday and make the QD repairs before resuming the oxidizer fill.

The Auxiliary Propulsion Unit (APU) hot fire is scheduled for tomorrow after the Rotating Service Structure (RSS) is moved to the parked position.

The Hubble payload will be transferred to the pad early Wednesday and will be installed onboard Columbia late this week.

Kennedy Space Center
Hubble Space Telescope
Payload Processing Status Report


Friday | Feb. 15, 2002
Loading of the Hubble payload into the canister was completed this morning. In the next couple of days, the canister will be rotated to an upright vertical position and embark on a 3 hour trip to the launch pad. CLICK HERE FOR MORE IMAGES...

Once at the pad, the payload will enter the Payload Changeout Room (PCR), which is adjacent to the Shuttle. Protective bagging will be removed. The payload will then undergo a contamination inspection and a trunnion inspection (to rule out sharp edges). CLICK HERE FOR MORE ON THE PAYLOAD CHANGEOUT...

 

Latest ::
Goto hubble.nasa.gov
Post-Mission ::
Late Apr
Mid Apr
Early Apr
Late Mar
Mission ::
Mar 12
Mar 11
Mar 10
Mar 9
EVA 5 : Mar 8
EVA 4 : Mar 7
EVA 3 : Mar 6
EVA 2 : Mar 5
EVA 1 : Mar 4
Mar 3
Mar 2
Mar 1
Pre-launch ::
Feb Week 4
Feb Week 3
Feb Week 2
Feb Week 1
Preparation ::
Late Jan
Mid Jan
Early Jan
Late Dec
Mid Dec
Early Dec
Late Nov
Mid Nov
Early Nov
Late Oct
Mid Oct
Early Oct
 
 
 
Glossary | FAQ | Links
| Page Last Updated: March 28, 2012 |
Links FAQ Glossary Home