Previous
Articles (August - November):
Kennedy
Space Center Space Shuttle Status Report - November 29, 1999
Kennedy
Space Center Space Shuttle Status Report - November 22, 1999
Kennedy
Space Center Space Shuttle Status Report - November 19, 1999
FloridaToday
- November 19, 1999: Discovery damage not thought to be
serious; pad fix possible
Excerpt
from Aerospace Daily: Article:144113
- Novemeber 19, 1999
Kennedy
Space Center Space Shuttle Status Report - November 15, 1999
NASA
Press Release - November 15, 1999: Hubble Telescope Placed
into Safe Hold as Gyroscope fails
FloridaToday
- November 15, 1999: Hubble in Safe Mode
FloridaToday
- November 14, 1999: Discovery makes trip to pad after
series of delays
FloridaToday
- November 13, 1999: Discovery rolling toward launch pad
FloridaToday
- November 12, 1999: Work performed to replace Discovery
engine
MSNBC
- November 10, 1999: Mission aimed at protecting space
telescope's science
Kennedy
Space Center Space Shuttle Status Report - November 9, 1999
Kennedy
Space Center Space Shuttle Status Report - November 8, 1999
Kennedy
Space Center Space Shuttle Status Report - November 5, 1999
Kennedy
Space Center Space Shuttle Status Report - November 4, 1999
FloridaToday
- Nov.4, 1999: Discovery rolls into the VAB
FloridaToday
- Nov. 4, 1999: Discovery's launch delayed to swap engine
NASA
Press Release - November 9, 1999: Preflight
Briefings for SM3A
Kennedy
Space Center Space Shuttle Status Report - October 29, 1999
FloridaToday - October 28, 1999:
Discovery's move to Vehicle Assembly Building delayed
The Next Servicing Missions
for HST: SM3A and SMOV3A
FloridaToday - October 5, 1999: Crucial
space shuttle wiring inspections continue
FloridaToday
- August 24, 1999: Hubble mission flight hardware arrives
at KSC
KENNEDY
SPACE CENTER SPACE SHUTTLE STATUS REPORT
MONDAY,
NOVEMBER 29, 1999 (2:30 PM EST)
MISSION: STS-103 -- 3rd HUBBLE SPACE TELESCOPE SERVICING MISSION
VEHICLE:
Discovery/OV-103 LOCATION: Pad 39B
TARGET KSC LAUNCH DATE/TIME: December 9 at 1:10 a.m. EST
TARGET KSC LANDING DATE/TIME: December 18 at about 10:40 p.m.
EST
LAUNCH WINDOW: 42 minutes
MISSION DURATION: about 9 days and 21 hours
CREW: Brown, Kelly, Smith, Foale, Grunsfeld, Nicollier, Clervoy
ORBITAL ALTITUDE and INCLINATION: 317 nautical miles/28.45
degrees
Note:
Last Wednesday, Shuttle workers closed Discovery's payload
bay doors and completed planned main engine testing. Repair
efforts on Discovery's umbilical wiring are complete and validation
tests begin tonight. Following the Thanksgiving holiday, workers
resumed orbiter electrical wiring inspections in Discovery's
aft compartment.
Today,
engineers will conduct the helium signature leak test. Ordnance
installation is slated to occur midweek and replacement of
a leaky quick disconnect on auxiliary power unit No. 2 is
planned for Wednesday evening. Aft engine compartment close-outs
are expected to conclude late Sunday. Workers are replacing
Discovery's mass memory unit No. 1 today.
Wednesday
afternoon, Shuttle managers will reconvene a follow-up Flight
Readiness Review to obtain a final status on prelaunch preparations.
The flight crew is scheduled to arrive at KSC's Shuttle Landing
Facility Saturday night, and the launch countdown begins Monday,
Dec. 6 at 5:30 a.m.
Major
Processing Milestones (targets only):
Ordnance installation ------------------------------(Dec.
1)
Flight crew arrival at KSC---------------------------(Dec.
4 at about 8 p.m.)
Orbiter aft compartment close-outs complete--------(Dec. 5)
Launch countdown begins--------------------------(Dec. 6 at
5:30 a.m.)
Kennedy
Space Center Space Shuttle Status Report
Monday,
November 22, 1999
(2:30 p.m. EST)
MISSION: STS-103 - 3rd Hubble Space Telescope Servicing Mission
VEHICLE: Discovery/OV-103
LOCATION: Pad 39B
TARGET KSC LAUNCH DATE/TIME: December 9 at 1:10 a.m. EST
TARGET LANDING DATE/TIME: December 18 at about 10:15 p.m.
EST
LAUNCH WINDOW: 42 minutes
MISSION DURATION: about 9 days and 21 hours
CREW: Brown, Kelly, Smith, Foale, Grunsfeld, Nicollier, Clervoy
ORBITAL ALTITUDE and INCLINATION: 317 nautical miles/28.45
degrees
Work
in progress: Shuttle managers today set December 9 as the
launch date for Discovery on STS-103. The adjusted launch
date allows technicians time to repair minor electrical wiring
damage that was found recently in an umbilical between the
Shuttle orbiter and the external tank. The schedule also allows
the Shuttle workforce to observe the Thanksgiving holidays.
Managers
plan to reconvene the STS-103 Flight Readiness Review on Dec.
1at 2 p.m. to obtain a final status on the recent work completed
on Discovery. Friday, workers at Launch Pad 39B completed
payload interface verification testing and today are conducting
the planned end-to-end test. Payload bay close-outs begin
this week and Discovery's payload bay doors will be closed
for flight Nov. 24.
Over
the weekend, oxidizer and fuel reactants were loaded into
Discovery's onboard storage tanks. Leak checks on Shuttle
main engine No. 3 are complete and good. Routine inspections
of Discovery's aft compartment are in work in preparation
for next week's orbiter aft close-outs.
Major
Processing Milestones (targets only):
Shuttle main engine test . . . . (Nov. 23)
Payload bay doors closed for flight . . . . (Nov. 24)
Shuttle Interface Test repeated . . . ..(Nov. 29)
Ordnance installation . . . ..(Dec. 1)
Orbiter aft compartment closed-out . . . .(Dec. 4)
Launch countdown begins . . . ..(Dec. 6)
Kennedy
Space Center Space Shuttle Status Report
Friday,
November 19, 1999 (8:30 p.m. EST)
MISSION: STS-103 - 3rd Hubble Space Telescope Servicing Mission
VEHICLE:
Discovery/OV-103
LOCATION: Pad 39B
TARGET KSC LAUNCH DATE/TIME: No earlier than Dec. 6 at 2:37
a.m. EST
TARGET LANDING DATE/TIME: Dec. 15 at 11:57 p.m. EST
LAUNCH WINDOW: 42 minutes
MISSION DURATION: 9 days and 21 hours
CREW: Brown, Kelly, Smith, Foale, Grunsfeld, Nicollier, Clervoy
ORBITAL ALTITUDE and INCLINATION: 317 nautical miles/28.45
degrees
NOTE:
Following today's Flight Readiness Review at KSC, managers
decided to keep the target launch date of no earlier than
Dec. 6 for mission STS-103. Managers plan to convene early
next week to further address potential changes to Discovery's
target launch date. Also, a follow-up Flight Readiness Review
will be held after the Thanksgiving Holiday weekend to permit
managers the opportunity to re-address outstanding engineering
issues and to establish an official launch date.
FloridaToday,
November 19, 1999
Discovery
damage not thought to be serious; pad fix possible
By
Robyn Suriano
CAPE CANAVERAL, Fla. - NASA has found more damaged electrical
wires on shuttle Discovery, officials said Thursday, prompting
new inspections on the ship as work continues toward a Dec.
6 launch to the Hubble Space Telescope. Officials don't know
yet if the checks and repairs will delay the liftoff, said
Kennedy Space Center spokesman Joel Wells. All the work can
be done while the shuttle sits on its launch pad, he said.
Described
as minor, the new damage was found on wiring between the spaceship,
its external tank and solid rocket boosters.
Technicians
found minor flaws in the insulation of wiring needed to relay
electrical power from the shuttle to the external fuel tank
and solid rocket boosters, Wells said. The discovery was made
after cracks were found in similar wiring aboard Endeavour.
The
solution could be as fast and easy as applying tape for extra
insulation, or could be much more complicated, Wells said.
All work can be done at the launch pad, he said.
Originally
scheduled in October, the flight was postponed when NASA ordered
wiring inspections on its entire fleet after shuttle Columbia
experienced a troublesome short circuit during a July launch.
"The
important thing here is that we are operating in an environment
of heightened awareness over wiring issues," Wells said. "We
are being very meticulous in our inspections."
When
launched, the ship is to carry seven astronauts to repair
Hubble's precision-pointing system.
Aerospace
Daily: Article:144113 - Novemeber 19, 1999
Hubble gyro glitch impacts about 100
observation projects
GODDARD
SPACE FLIGHT CENTER, Md. - Scientists on about 100 different
projects counting on the Hubble Space Telescope for data will
have to wait at least a little longer for their observations
because of last weekend's gyroscope failure, the Hubble senior
scientist said yesterday. David Leckrone told The DAILY the
observations postponed when the orbiting telescope went into
a sun-pointing safe mode will be rescheduled "as soon as possible,"
given the complex nature of Hubble scientific operations.
Observations are scheduled to make the most efficient use
of telescope time while keeping it available to observe transient
events.
The
number of science projects impacted by the long-feared gyro
failure could grow if the down-time extends beyond the three
weeks presently planned for the crew of the Space Shuttle
Discovery to reach the Hubble and replace all six gyros on
it. If Discovery cannot get off the ground for its urgent
Hubble servicing mission by mid-December, NASA probably won't
fly until next year out of concern for the Year 2000 date-
logic problem (DAILY, Nov. 15, 16).
Hubble
engineers here told reporters yesterday AlliedSignal has changed
the way it manufactures its highly accurate gyros in an effort
to stretch their service lives to prevent a future shutdown.
But the basic design of the gyros has not changed, since they
are about twice as accurate as the next-best gyros available,
according to Hubble Program Manger John Campbell. The problem
is the tiny leads that carry power to the gyro rotors. Sunk
in a thick damping fluid, the hair-like wires corrode over
time and break. The six new gyros Discovery's crew will install
retain the fine power leads, but the damping fluid was loaded
into the gyros in a manner that engineers hope kept oxygen
out of the system, reducing the risk of oxidation.
In
the past the gyros have lasted four to six years, which has
been enough to keep Hubble pointing accurately between servicing
missions since only three of the six are needed for science
operations. NASA split the third Hubble servicing mission
in two last March when the third gyro failed as a way to get
the whole set replaced in time to maintain science operations
(DAILY, March 11).
But
with the Shuttle fleet grounded this fall for unanticipated
wiring inspections and repairs, time ran out and the telescope
dropped to only two functioning gyros. The gyros are needed
to keep the telescope pointed with extreme precision at distant
points in the sky to collect data from faint sources for as
long as 10 days, Campbell explained. Maintenance and upgrades.
The
STS-103 mission on Discovery will devote its four spacewalks
to upgrading and maintaining the systems on the telescope
spacecraft, rather than its scientific instruments. In addition
to replacing the six gyros and related equipment, Discovery's
crew will install a new main computer; circuitry to deal with
battery overheating; a second solid-state data recorder; a
new S-band single-access transmitter, and new fine-guidance
sensors to pick out the guide stars used in telescope pointing.
Spacewalking
astronauts broken into two two-person teams will also apply
lubricant to balky door latches and, on the last day outside,
install new sheets of thermal-protection material over old
material that has deteriorated in the space environment.
Before
the mission was split, plans called for the astronauts to
install a new "Advanced Camera for Surveys" (ACS) on the telescope
next summer. Senior scientist Leckrone said the new camera
will have what is called a "discovery efficiency" 10 times
better than existing instruments. The new instrument, being
built by Ball Aerospace in Boulder, Colo., is now scheduled
to be installed in the summer of 2001.
The
new camera will have a wider field of view and better resolution
than the present Wide Field Planetary Camera that has produced
many of Hubble's most spectacular images to date, Leckrone
said. It will be particularly useful in the search for the
cold dark matter cosmologists believe makes up the "missing
mass" of the Universe, making use of the gravitational lensing
the Hubble has demonstrated is fairly common.
"When
you have a distant galaxy or quasar and then you have a cluster
of galaxies in the foreground, the mass of that cluster...actually
focuses the light from the more distant galaxy or quasar into
an image that we see," Leckrone said. "...If I now look at
one of these foreground clusters of galaxies that's doing
this lensing, and I look at the brightness of lenses and where
they're located and their extent, that tells me immediately
how much mass is in the lens, and how that mass is distributed
within the cluster of galaxies and probably by a factor of
30 to 1 that mass is cold dark matter, unseen matter of a
kind that we haven't characterized...I think that is one of
the big programs this camera will be just perfect for."
-
Frank Morring Jr.
Kennedy
Space Center Space Shuttle Status Report
Monday,
November 15, 1999 (12:30 p.m. EST)
MISSION: STS-103 - 3rd Hubble Space Telescope Servicing Mission
VEHICLE:
Discovery/OV-103
LOCATION: Pad 39B
TARGET KSC LAUNCH DATE/TIME: December 6 at 2:37 a.m. EST
TARGET LANDING DATE/TIME: December 15 at 11:57 p.m. EST
LAUNCH WINDOW: 42 minutes
MISSION DURATION: 10 days and 21 hours
CREW: Brown, Kelly, Smith, Foale, Grunsfeld, Nicollier, Clervoy
ORBITAL ALTITUDE and INCLINATION: 317 nautical miles/28.45
degrees
Work
in progress: Space Shuttle Discovery rolled out to Launch
Pad 39B on Saturday, Nov. 13. First motion from the Vehicle
Assembly Building began a 7:27 a.m. and the Shuttle was hard
down at the pad by 2:17 p.m. Discovery had been scheduled
to begin its transfer to the pad at 2 a.m., but inspections
of minor external tank foam damage delayed the departure.
While
Discovery was in the VAB, workers completed efforts to replace
Shuttle main engine No. 3 and the solid rocket booster range
safety cable. The Shuttle Interface Test validated all Space
Shuttle connections prior to rollout. Final checks of the
replaced main engine will be completed at the pad. Launch
pad validations are under way and installation of the payload
into Discovery's payload bay is slated for tomorrow.
The
seven-member flight crew arrived at KSC Sunday afternoon and
will participate in Terminal Countdown Demonstration Test
activities through Wednesday. The launch day dress rehearsal
concludes Wednesday at 11 a.m. with a simulated main engine
cutoff. Shuttle managers will convene the STS-103 Flight Readiness
Review on Friday, Nov. 19 to discuss the overall readiness
of all Space Shuttle systems for flight.
Major
Processing Milestones (targets only): Payload installed
into orbiter |
Nov.
16 |
Terminal
Countdown Demonstration Test (crew dress rehearsal) |
Nov.
17 |
Flight
Readiness Review |
Nov.
19 |
Shuttle
main engine test |
Nov.
23 |
NASA
Press Release, November 15, 1999
Hubble
Telescope Placed into Safe Hold as Gyroscope Fails
NASA's Hubble Space Telescope was placed into a safe hold
at approximately 8:30 a.m. EST Saturday morning when gyroscope
#1 ceased operation. With only two operational gyros remaining,
the science program will be suspended until completion of
Servicing Mission 3A, currently scheduled for launch aboard
Space Shuttle Discovery on Dec. 6, 1999.
This
gyro situation is not expected to impact the upcoming servicing
mission. In fact, anticipation that another gyro could fail
was the primary reason that Hubble managers scheduled an early
repair mission and split the third servicing mission activities
into two flights: Servicing Mission-3A (Dec. 6, 1999) and
Servicing Mission-3B (Mid-2001).
"This
event underscores the wisdom of dividing the third HST Servicing
Mission into two parts, with Servicing Mission 3A scheduled
for December 1999 -- only 3 weeks of science data will be
lost," said Dr. John Campbell, Hubble Space Telescope Program
Manager at NASA's Goddard Space Flight Center, Greenbelt,
MD.
The
safe-hold mode has been thoroughly tested and used twice since
Hubble's launch in 1990. The telescope is not at risk. This
protective safe mode allows ground control of the telescope,
but with only two gyros working, Hubble cannot be aimed with
the precision necessary for scientific observations of the
sky.
The
safe mode does not require gyros, so even if another gyro
should fail in the next few weeks, HST will remain safe, according
to project managers. The aperture door has been closed to
protect the optics, and the spacecraft is aligned to the sun
to ensure adequate power is received by Hubble's solar panels.
Engineers
are investigating the cause of the gyro loss. The gyro will
be returned to ground after the upcoming servicing mission
for in-depth analysis.
During
Servicing Mission 3A, astronauts will replace all the gyroscopes,
a fine guidance sensor, a transmitter, a spare solid- state
recorder and a high-voltage/temperature kit for protecting
batteries from overheating. Additionally, the crew will install
an advanced computer.
Servicing
Mission 3B will be conducted in 2001 to complete the third
HST servicing mission activities.
FloridaToday,
November 15, 1999
Monday,
November 15, 1999 Update for 10:26 a.m. EST:
Hubble
in Safe Mode
NASA's Hubble Space Telescope temporarily has halted its science
work after the failure this weekend of equipment that helps
the observatory lock onto stars and other objects, officials
said Monday. In safe mode, the telescope is in no danger,
but it won't be able to do any observations work until spacewalking
astronauts from shuttle Discovery make some repairs next month
on a planned Dec. 6 mission. "The telescope is in good shape,
we're getting telemetry and everything else is showing good
indications that the spacecraft is in good health," said Don
Savage from NASA headquarters in Washington, D.C. The telescope
carries six devices called gyros that allow it to be pointed
at its celestial targets. Three are needed to keep the telescope
stable for its precision pointing during science work. Three
of the devices had failed already, and a fourth gyro stopped
working on Saturday, said John Campbell, Hubble's project
manager at the Goddard Spaceflight Center in Greenbelt, Md.
That means about six weeks' loss of science work until the
repairs are made and Hubble can resume operations sometime
in January, he said. - Robyn Suriano
FloridaToday,
November 14, 1999
Discovery
makes trip to pad after series of delays
CAPE
CANAVERAL, Fla. - Space shuttle Discovery is sitting on its
launch pad today as NASA begins final preparations for next
month's flight to the orbiting Hubble Space Telescope. - Justin
Ray
|
|
|
|
|
|
|
Towering
atop the mobile launcher platform and crawler transporter,
Discovery rolls out of the Vehicle Assembly Building on
Saturday morning. NASA images. |
FloridaToday
- Nov.13, 1999
Discovery
rolling toward launch pad
Update
for 9:25 a.m. EST KENNEDY SPACE CENTER, Fla. - Space shuttle
Discovery emerged from Kennedy Space Center's Vehicle Assembly
Building this morning bound for launch pad 39B at the edge
of the Atlantic Ocean. The 6-hour, 4.2-mile trek began at
7:27 a.m. EST. The spaceship is riding atop a mobile launching
platform with a cruising speed of one mile per hour. Discovery
will be going much faster on Dec. 6 when its lifts off on
a 10-day mission to service and upgrade the Hubble Space Telescope.
-Justin Ray
FloridaToday
- Nov.12, 1999
Work
performed to replace Discovery engine
Work was performed inside the Kennedy Space Center Vehicle
Assembly Building to replace main engine No. 3 (left) on shuttle
Discovery. Last week, Shuttle managers determined that the
engine was not acceptable for flight because a half-inch-long
broken drill bit is lodged in the engine's coolant cavity.
Therefore, the engine is being replaced. Discovery is expected
to roll out to the pad at 2 a.m. Saturday morning The STS-103
launch is now targeted for Dec. 6 at 2:37 a.m. EST. The 10-day
mission is expected to conclude at KSC on Dec. 16 with a 12:45
a.m. landing. NASA images.
Hubble
repairmen are ready to fly - Nov. 10, 1999
Mission aimed at protecting space telescope's
science
By Alan Boyle
MSNBC
Imagine hooking up a stereo system inside a broom closet ...
while you're wearing a spacesuit with heavy gloves. Multiply
the expense and aggravation by a factor of, say, 100,000,
and you'll get an idea of the challenge facing four astronauts
during next month's mission to repair the Hubble Space Telescope.
THE
FACT that the launch date for the shuttle Discovery still
isn't set in stone could justifiably add to the aggravation:
So far, mechanical problems have delayed the start of this
third Hubble servicing mission, originally scheduled for October,
until Dec. 6. A wiring problem could still set the flight
back even further. Even though the delay provided some extra
time at the end of a relatively rushed training schedule,
Discovery pilot Scott Kelly said "it was a little disappointing,
because we did work so hard and were ready to fly in October."
But
Kelly and his six crew mates said during a Tuesday news conference
at NASA's Johnson Space Center that they weren't letting the
technical snags get them down. "We as a crew have been trained,
we have confidence in our team ... and when the orbiter is
ready to go, we'll be ready to go," said commander Curt Brown.
FIX-IT
MISSION
Although
NASA stresses this isn't an emergency mission, Discovery's
10-day flight is designed to respond to a pressing problem:
the fact that three of Hubble's six gyroscopes are broken.
One more gyroscope failure would force a halt to the flow
of images and scientific data from the telescope NASA regards
as the crown jewel of astronomical observation.
The
trickiest jobs may belong to Discovery's two sets of spacewalkers:
John Grunsfeld and Steven Smith (a veteran of the second Hubble
servicing mission in 1997), British-American astronaut Michael
Foale and Swiss astronaut Claude Nicollier (who was on the
first Hubble servicing mission in 1993).
"The
clearances are very small," noted Smith, who is supposed to
angle himself within the telescope to switch out the faulty
gyroscopes.
One
of Nicollier's jobs will be to roll new sheets of thermal
protective covering over the 43-foot-long (13.1-meter-long)
telescope's outer hull. "It's going to be pretty much like
putting wallpaper on your wall at home," he said. But instead
of applying wallpaper paste, the spacewalkers will use cables
and clips to keep the sheets in place.
Foale
noted that he had to help keep 340 tools organized for the
mission's four spacewalks. He also has the task of unhooking
the telescope's outdated computer and installing a new model
using a radiation-hardened Intel 486 processor - a task that
requires matching up delicate connectors while wearing those
bulky spacesuit gloves.
Smith
and Grunsfeld have to replace a broken S-band transmitter
under similarly awkward conditions. Nicollier will install
a new Fine Guidance Sensor to help Hubble stay focused on
dim objects - an instrument that Foale said was the size of
a baby grand piano.
Among
the other equipment to be installed: voltage kits to keep
the telescope's six batteries from overheating, a new solid-state
data recorder to replace a less reliable mechanical recorder
and a protective blanket that looks like a huge, curved cookie
sheet.
Grunsfeld
said the gloves and spacewalking suits were likely to be much
stiffer than the suits used during hundreds of hours of pre-flight
training. But he almost sounded as if he looked forward to
the awkward exercise.
"I
grew up on the South Side of Chicago, and I used to love to
get dressed up in all my winter clothing. I thought that was
a lot of fun. It's very much like that," Grunsfeld said.
French
astronaut Jean-Fran�ois Clervoy, who is to operate the shuttle's
robot arm, rounds out Discovery's crew.
SAVING
THE SCIENCE
NASA
officials acknowledged that the general public might not see
a dramatic change in the quality of Hubble images as a result
of the crew's efforts.
"We're
really not making any scientific improvements in this mission,"
said Ed Weiler, the space agency's associate administrator
for space science. "This mission is really to protect the
science."
But today there is far more science to protect than when Hubble
was deployed from Discovery in 1990, noted John Campbell,
Hubble program manager at NASA's Goddard Space Flight Center.
The amount of science data returned by the telescope is 11
times what it was in 1991, he said.
Two more servicing missions are scheduled: During a 2001 flight,
a new Advanced Camera for Surveys is to be installed, as well
as a cooling system that could revive Hubble's near-infrared
camera and spectrometer. A final 2003 mission would bring
up a Cosmic Origins Spectrograph and spruce up the telescope
for service through the year 2010.
And then what? By then, NASA's Next Generation Space Telescope
should be up and running. Hubble might be boosted into a higher
orbit to keep it out of the way - or it could be loaded aboard
the space shuttle, brought back to Earth and placed in a museum,
Weiler said.
Weiler
estimated the cost of Discovery's servicing mission at $136
million, and said the projected total expense for the Hubble
mission - including 10 years of development and 20 years of
operation - would amount to $6 billion.
"That's
an average cost of $200 million a year from 1980 to 2010,"
he said, "and that equates to about 2 cents per week per American
for Hubble."
Kennedy
Space Center
Space Shuttle Status Report
Monday,
November 9, 1999 (11:30 a.m. EST)
MISSION: STS-103 - 3rd Hubble Space Telescope Servicing Mission
VEHICLE:
Discovery/OV-103
LOCATION: VAB
TARGET KSC LAUNCH DATE/TIME: December 6 at 2:37 a.m. EST
TARGET LANDING DATE/TIME: December 16 at 12:45 a.m. EST
LAUNCH WINDOW: 42 minutes
MISSION DURATION: 10 days
CREW: Brown, Kelly, Smith, Foale, Grunsfeld, Nicollier, Clervoy
ORBITAL ALTITUDE and INCLINATION: 317 nautical miles/28.45
degrees
Work
in progress: Space Shuttle Discovery is scheduled to roll
out to Launch Pad 39B on Saturday, Nov. 13, with first motion
slated for 2 a.m. The remainder of Discovery's processing
schedule leads to a target launch date of Dec. 6.
Workers
have already removed the damaged range safety cable and replacement
efforts begin later today. Engineers plan to retest the range
safety system Wednesday and close-out the work area Thursday.
The damaged range safety cable relays a redundant emergency
destruction signal between the solid rocket boosters (SRB)
in the unlikely event of a contingency. The cable being replaced
runs from the right-hand SRB forward attach point, through
the external tank and connects to the left-hand booster. The
cable was damaged during close-out operations causing yesterday's
test failure.
Since
the orbiter will remain in the VAB for cable replacement,
Shuttle managers have decided to replace Discovery's main
engine No. 3 in the VAB as well. Engine replacement efforts
are in work and will conclude Thursday. Engine close-outs
and verifications will be performed at the pad.
The
Hubble Servicing Mission cargo has been transferred into the
payload change-out room at Launch Pad 39B and installation
into the orbiter's payload bay is slated for Nov. 16.
Major
Processing Milestones:
Shuttle
to the Launch Pad |
Nov.
13 |
Payload
installed into orbiter |
Nov.
16 |
Terminal
Countdown Demonstration Test (crew dress rehearsal) |
Nov.
17 |
Shuttle
main engine test |
Nov.
23 |
Kennedy
Space Center
Space Shuttle Status Report
Monday,
November 8, 1999 (4:00 p.m. EST)
MISSION: STS-103 - 3rd Hubble Space Telescope Servicing Mission
The
planned rollout of Space Shuttle Discovery to Launch Pad 39B
has been delayed beyond Tuesday, Nov. 9. During standard Shuttle
Interface Test activities this morning, engineers in firing
room No. 1 noted loss of command capability for a range safety
cable that supports both solid rocket boosters. Subsequent
visual inspections revealed damage to the SRB cross-strap
cable that runs between the external tank (ET)/SRB attach
points and through the ET intertank.
KSC
managers have decided to replace the cable and are developing
a plan to accommodate the unexpected work. The impact of this
work on the remainder of Discovery's processing schedule is
being assessed. Preliminary reports indicate that an early
December launch date is still achievable.
The
Hubble Servicing Mission cargo was transported to the launch
pad early this morning and transfer into the payload change-out
room is in work.
Kennedy
Space Center
Space Shuttle Status Report
Thursday,
November 5, 1999 (4:00 p.m. EST)
MISSION: STS-103 - 3rd Hubble Space Telescope Servicing Mission
Work
in progress: Orbiter Discovery has been mated to the external
tank and solid rocket boosters stack in VAB high bay 1. Electrical
and mechanical connections will conclude late Friday and the
orbiter/external tank umbilical mate occurs Saturday. Over
the weekend, workers will begin preparations for the engine
No. 3 replacement work scheduled to happen at the launch pad.
Managers currently plan to transfer Discovery out to Launch
Pad 39B Tuesday, Nov. 9 beginning at about 2 a.m.
Payload
managers plan to transfer the Hubble Servicing Mission cargo
to the launch pad Monday, Nov. 8 with installation into the
orbiter slated for Nov. 12.
KSC
managers are developing the remainder of Discovery's prelaunch
processing schedule and expect to brief Shuttle program managers
at a meeting Monday morning. Program managers are likely to
set a new target launch date for STS-103 after the meeting.
Kennedy
Space Center
Space Shuttle Status Report
Thursday,
November 4, 1999
MISSION:
STS-103 - 3rd Hubble Space Telescope Servicing Mission
VEHICLE:
Discovery/OV-103
LOCATION: Vehicle Assemble Building
TARGET KSC LAUNCH DATE/TIME: early December (under review)
TARGET LANDING DATE/TIME: mid December (under review)
LAUNCH WINDOW: 42 minutes
MISSION DURATION: 10 days
CREW: Brown, Kelly, Smith, Foale, Grunsfeld, Nicollier, Clervoy
ORBITAL ALTITUDE and INCLINATION: 317 nautical miles/28.45
degrees
Work
in progress: Orbiter Discovery rolled out of OPF bay 1 today
at about 10 a.m. Later tonight, workers will begin efforts
to mate the orbiter to the external tank and twin solid rocket
boosters located in VAB high bay 1. Current work plans show
the Space Shuttle rolling out to Launch Pad 39B early next
week. Once at the pad, preparations to replace Shuttle main
engine No. 3 will begin. Managers expect that effort to take
about 10 days, with most of the work done in parallel with
other prelaunch work.
Shuttle
managers are assessing the remainder of Discovery's processing
schedule and expect to announce a new target launch date next
week.
FloridaToday
- Nov.4, 1999
Update for 10:55 a.m. EST
Discovery
rolls into the VAB
By
Justin Ray
Space shuttle Discovery departed its processing hangar just
after 10 a.m. EST this morning and headed into the Vehicle
Assembly Building. Discovery made the 40-minute trip riding
atop a 76-wheel transporter originally built to move space
shuttles through the mountains at Vandenberg Air Force Base
in California. Later today in the VAB, Discovery will be hoisted
vertically and moved into position to be mated with the awaiting
external fuel tank and solid rocket boosters. Rollout to launch
pad 39B is planned for the middle of next week.
Meanwhile,
NASA spokesman Joel Wells now says that the drill bit lodged
in Discovery's main engine No. 3 was broken earlier this spring
at Kennedy Space Center. Previously provided information said
the incident occurred two or three months ago at Rocketdyne's
Canoga Park plant in California. NASA officials decided yesterday
that the engine would be replaced before Discovery's mission,
which will delay the planned Dec. 2 launch date by a few days.
|
|
|
|
Orbiter
Discovery rolls out of Orbiter Processing Facility bay
1 Thursday morning at Kennedy Space Center bound for the
Vehicle Assembly Building. Processing of Discovery for
launch on STS-103 continues toward an early December liftoff
on the third mission to service the Hubble Space Telescope. |
FloridaToday
- Nov.4, 1999
Discovery's launch delayed to swap engine
By
Justin Ray
CAPE
CANAVERAL, Fla. - Shuttle Discovery's already delayed mission
to repair the Hubble Space Telescope will be pushed back at
least a few days next month so one of its engines can be replaced.
The
work has to be done because the engine has a piece of a drill
bit lodged in one cooling tube, NASA officials said Wednesday.
The
tiny piece broke off several months ago while the engine was
undergoing routine maintenance at Kennedy Space Center earlier
this spring.
The
bit initially was not considered dangerous, but officials
reconsidered Wednesday and decided to switch the engine after
Discovery is moved to its launch pad next week.
That
will delay it from its intended Dec. 2 launch. A new date
could be selected as early as today.
"It
was basically a decision on the side of caution," said NASA
spokesman Joel Wells. "We said, `Wait a minute, are we sure
this thing isn't going to get loose in there and cause us
a problem?' "
Discovery's
trouble is the latest in a string of incidents to hit the
fleet.
In
July, a pin broke loose inside a main engine aboard shuttle
Columbia and ruptured tubes in one nozzle during launch, allowing
fuel to leak out.
Exposed
wiring in Columbia also caused an electrical short that shut
down some of the computers controlling the ship's main engines.
Back-up
computers took over and the ship made it safely to orbit.
However, the shuttle was only one failure away from attempting
an emergency landing in Africa.
The
wiring glitch forced a fleetwide inspection, and repairs had
to be made to exposed wire in 57 places in Discovery. The
repairs already have delayed Discovery from a planned October
liftoff.
In
yet another matter, technicians last week accidentally damaged
flaps on shuttle Atlantis' wings during routine checks. NASA
called the damage minor.
Outside
safety experts expressed some concern Thursday over the incidents,
which come in a year when NASA has made just two shuttle flights
- the fewest since 1988 when the ships returned to service
after the Challenger disaster.
Still,
they said NASA is doing everything in its power to play it
safe.
"Being
worried is fine, you have to be worried," said Seymour Himmel,
a member of the Aerospace Safety Advisory Panel, an independent
group of experts that oversees NASA for Congress.
"But
the way to deal with worry is to take the necessary steps
to prevent problems, and I believe the KSC people and the
shuttle people have done everything possible to ensure the
efficacy of their workforce and the safety of these birds."
NASA
Press Release, November 1, 1999
Preflight
Briefings for Hubble Servicing Mission Set for November 9
Background briefings on the upcoming Space Shuttle mission
to service the Hubble Space Telescope will be held on Tuesday,
Nov. 9.
The
mission, designated STS-103, will mark the third visit of
a Space Shuttle crew to Hubble and features four scheduled
spacewalks by two teams of astronauts. Each spacewalk will
last approximately six hours as the astronauts install new
gyroscopes, upgraded sensors, computers and recorders. The
teams also will install a new transmitter, add voltage/temperature
improvement kits for the telescope's batteries, and begin
repair of the insulation on the telescope's outer surface,
which has deteriorated during nine years in orbit.
The
briefings will begin at 9 a.m. EST with an overview of the
mission objectives and spacewalk tasks. That will be followed
at 11 a.m. by a briefing on Hubble hardware and science originating
from NASA Headquarters. Following the NASA Video File at noon,
the STS-103 astronauts will hold their press conference at
2 p.m. All of the briefings will be carried live on NASA Television.
NASA
Television is available through the GE-2 satellite, transponder
9C, located at 85 degrees West longitude, vertical polarization,
with a frequency of 3880 MHz, and audio at 6.8 MHz.
Following
the mission briefings, round-robin interviews with the crewmembers
will be held for reporters at NASA's Johnson Space Center
in Houston and for those reporters who make advance arrangements
to participate by telephone. Media wishing to participate
in the round-robin interviews must fax their request to the
Johnson Newsroom by close of business on Friday, Nov. 5. The
fax number is 281/483-2000.
STS-103
PRE-FLIGHT BRIEFINGS
Tuesday, Nov. 9, 1999
(All times shown are EST)
9
a.m. |
Mission
Overview and Spacewalk Briefing
Linda Ham, Lead Flight Director, Johnson Space Center
Keith Johnson, Lead EVA Officer, Johnson Space Center
|
11
a.m. |
Hubble
Space Telescope Payload and Science Briefing
Dr. Edward Weiler; Associate Administrator for Space Science;
NASA Headquarters; Washington, DC
Dr. John Campbell; Hubble Project Manager; Goddard Space
Flight Center; Greenbelt, MD
Debra Henretty; Engineer; Guidance, Navigation and Control
Center; Goddard Space Flight Center
Dr. Anne Kinney; Director, Astronomical Search for Origins;
NASA Headquarters
|
Noon |
NASA
TV Video File
|
2
p.m. |
STS-103
Crew Press Conference
Curt Brown, Commander
Scott Kelly, Pilot
Steve Smith, Payload Commander, Mission Specialist (MS)1
Jean-Francois Clervoy, MS2
John Grunsfeld, MS3
Mike Foale, MS4
Claude Nicollier, MS5
|
3
p.m. |
STS-103
Crew Round-Robin Interviews
These interviews will not be carried on NASA TV. |
Kennedy
Space Center
Space Shuttle Status Report
Monday,
October 29, 1999 (3:30 PM EDT)
MISSION: STS-103 - 3rd Hubble Space Telescope Servicing Mission
VEHICLE:
Discovery/OV-103
LOCATION: OPF bay 1
TARGET KSC LAUNCH DATE/TIME: Dec. 2 at 4:31 a.m. EST
TARGET LANDING DATE/TIME: Dec. 12 at 2:38 a.m. EST
LAUNCH WINDOW: 42 minutes
MISSION DURATION: 9 days, 22 hours and 7 minutes
CREW: Brown, Kelly, Smith, Foale, Grunsfeld, Nicollier, Clervoy
ORBITAL ALTITUDE and INCLINATION: 317 nautical miles/28.45
degrees
Work
in progress: Shuttle managers will resume discussions on Monday
at 1 p.m. to determine Discovery's readiness to leave the
Orbiter Process Facility. The orbiter's planned transfer to
the Vehicle Assembly Building will now occur no earlier than
Monday evening. The postponement accommodates unplanned work
to repair a temperature sensor on Discovery's No. 2 nitrogen
tank, in the orbiter's midbody.
Retests
of Discovery's repaired and protected wiring are ongoing and
will continue through the vertical processing flow. Several
standard prelaunch tests will accommodate necessary functional
and redundancy checks of the wiring. Once the orbiter, external
tank and booster mating operations are complete, Space Shuttle
Discovery will roll out to Launch Pad 39B. Rollout to the
pad is currently slated for Sunday, Nov. 7.
FloridaToday
- Oct. 28, 1999
Discovery's move to Vehicle Assembly
Building delayed
By Justin Ray
CAPE
CANAVERAL, Fla. - Space shuttle program managers today decided
to delay Discovery's departure from its hangar by one day
so workers can replace a faulty sensor.
The
shuttle is now scheduled to be rolled from the Orbiter Processing
Facility bay 1 to the Vehicle Assembly Building on Tuesday
to be attached to an external fuel tank and twin solid rocket
boosters atop a mobile launch platform.
Last
week, technicians found a temperature sensor in the shuttle's
nitrogen tank No. 2 was not working properly, NASA spokesman
Joel Well said. "It was not something that had to do with
flight safety. But since we are still in the OPF, we decided
to replace it anyways."
The
one day delay isn't expected to impact Discovery's planned
Dec. 2 launch on the third mission to service NASA's Hubble
Space Telescope.
Officials
will meet on Monday to review the sensor replacement work
and establish a timeline to ready the shuttle to meet its
launch date.
For
now, Discovery is still slated to roll out to launch pad 39B
on Nov. 7.
NASA
said prior to this latest hiccup that it had two days of padding
left in the pre-launch schedule in order to meet a Dec. 2
liftoff. Two more days were also left open for holidays. Monday's
meeting will reassess exactly how much "contingency" time
is left to work any further problems that might arise, Wells
said.
Discovery's
flight, which will feature four spacewalks performed by two
pairs of astronauts to replace equipment aboard Hubble, has
been on hold while the entire shuttle fleet underwent inspections
and repairs for wiring defects.
The
Next Servicing Missions for HST: SM3A and SMOV3A
Carl Biagetti, STScI, biagetti@stsci.edu
The
following is a reprint from the September 1999 Newsletter
of the Space Telescope Science Institute.
HST's
Third Servicing Mission (SM3), until recently scheduled for
mid-2000, had originally been designed to provide for the
upgrade of the observatory's scientific capabilities, the
restoration of lost scientific capabilities, and the replacement
or refurbishment of degraded spacecraft subsystems.
- The
scientific upgrade was to result from the installation of
the Advanced Camera for Surveys (ACS) in the radial position
currently occupied by the Faint Object Camera (FOC), which
would be removed and returned to Earth. Restoration of scientific
capabilities was to be achieved by inclusion of the NICMOS
Cooling System (NCS) which would, after the mission, afford
the revival the NICMOS instrument.
- The
Pointing Control System (PCS) would benefit from a refurbished
Fine Guidance Sensor (FGS-2R) and a complete replacement
of the current complement of gyroscopes used for spacecraft
rate sensing.
- The
Data Management System was to be enhanced with the change-out
of the DF-224 computer, used for spacecraft control, with
a 486 replacement. Also, one of the original mechanical
tape recorders, now outmoded by the great increase in telescope
data volume, would be replaced by a second Solid State Recorder
(SSR-3), whose 12Gb capacity enables it to serve as a back-up
to the the previously-installed SSR-1.
- The
Electrical Power System (EPS) would be upgraded by replacement
of the current solar arrays with new, more efficient ones
(SA III) which will serve to increase spacecraft power while
reducing servicing risk and orbital drag. Additionally,
control of spacecraft battery temperatures will be improved
by the installation of the Voltage/Temperature Improvement
Kit (VIK).
- The
Thermal Control System (TCS) would be greatly enhanced by
the addition of an Aft Shroud Cooling System (ASCS) which
will guarantee years of three-instrument parallel science
through reduction of aft shroud instrument temperatures.
In addition, telescope ambient temperatures would be reduced
by the replacement of the degraded Multi-Layer Insulation
(MLI) at several external points on the spacecraft.
- The
Communications subsystem would be restored to its original
capability by the replacement of the failed S-Band Single
Access Transmitter (SSAT).
Obviously,
this was to be an ambitious servicing mission requiring
six full extra-vehicular activities (EVAs) to accomplish
all the replacements and refurbishments. Plans however
changed drastically on April 20, 1999 with the hard failure
of gyro 3. With this failure HST was reduced to three
operating gyros (out of an original complement of six),
the bare minimum for pointing control accurate enough
for scientific operations. While the reason for this and
the previous gyro failures was understood to be related
to a particular lot and fabrication process, the remaining
operational gyros were not subject to this flaw. Nonetheless,
any additional gyro failures would mean the end of HST
science until new gyros could be installed. For this reason,
the HST Project requested and was granted a "contingency"
mission, scheduled for October 1999, with the baseline
purpose of replacing all six gyros. Once authorized, this
new mission afforded the opportunity to off-load the heavily
booked SM3 with, in addition to the gyros, any other replacements
and refurbishments which would be ready by October.
As
a result, the original SM3 is now divided into two missions;
SM3A, scheduled for October 14, 1999, and SM3B scheduled,
as of this writing, for late 2000.
SM3A
is manifested for the installation of all six replacement
gyros, the refurbished FGS-2R, the VIK, the 486 computer,
SSA transmitter, and the SSR. In addition to these installations,
the MLI repair is scheduled as a lower priority, as is
the opening of the NICMOS valves to allow venting in preparation
for the installation of the NCS in SM3B.
All
other installations and refurbishments, including the
science upgrades, i.e., ACS and NCS/NICMOS, are scheduled
for SM3B. Also, SM3B will include an orbital reboost to
restore some of HST's orbital altitude.
SM3A
will be performed in Shuttle Mission STS-103, Shuttle
flight #97 using the Shuttle Orbiter Discovery (flight
#27). Launch will occur at 5:42 a.m., EDT, with a launch
window of 42 minutes, from Pad 39B at the Cape. The launch
duration is a little less than 10 days, with landing scheduled
for October 24, 3:20 a.m., also at the Cape. The mission
commander is Curtis L. Brown. The other six crew members
are Pilot Scott J. Kelly, and Mission Specialists Steven
L. Smith, C. Michael Foale, John M. Grunsfeld, Claude
Nicollier (Switzerland/ESA), Jean-Francois Clervoy (France/ESA).
On
flight day 3, a little more than 48 hours after launch,
the Shuttle will rendezvous with and capture HST. (The
observatory will continue doing science observations up
until just a few hours prior to this point.)
Then,
on flight day 4, approximately sixty-six hours into the
mission, the first of four six-hour EVAs, one per day,
will commence. This first EVA is scheduled to include
installation of the replacement gyros, the VIK, and the
opening of the NICMOS vent valves. The next day, the second
EVA will see the installation of the 486 computer and
the refurbished FGS-2R. EVA-3 will provide for the installation
of the SSA Transmitter and the new SSR. It will also allow
the first set of MLI upgrades on the external surfaces
of bays 5-10. The fourth EVA will consist of a set of
optional tasks, to be performed on a non-interference
basis, that include more MLI replacement on the telescope's
forward shell and light shield, and other lower priority
activities such as installation of handrail covers and
aft shroud latch replacement for +V2 doors.
Following
the installation of the new devices, the astronauts and
the ground operations personnel will conduct aliveness
tests to confirm proper connector seating and basic aliveness,
as well as functional tests to verify basic mission-critical
functions.
HST
is released from the Shuttle on flight day 8 and two days
later the Shuttle returns to KSC. While SM3A consists
of a substantial list of varied activities and installations,
the minimum success criterion is the installation of four
of six gyros. Replacement of all six gyros will constitute
a fully successful mission.
At
the point of release from the Shuttle early on October
21, the suite of activities and tests to recommission
the observatory for normal operations begins. This suite
of tests and the period in which they are performed are
called the Servicing Mission Observatory Verification
(SMOV).
In
general, the goal of any SMOV plan associated with HST
servicing consists of the timely recommissioning of the
Observatory for science operations. In the case of SM3A,
this goal takes the form of the commissioning of the FGS-2R
as a newly installed instrument, the recommissioning of
the existing science instruments which, in this case,
include the WFPC2, STIS, and FGS-1R (as the current astrometer).
It also includes the recommissioning of any spacecraft
subsystems affected by servicing. In this case, the goal
includes commissioning of the new gyros into the PCS system,
re-verification of the DMS with the new computer and SSR,
and re-verification of the EPS following the VIK installations.
The TCS and overall ambient temperatures will be monitored
pursuant the MLI upgrades. A major goal of any SMOV is
the demonstration of any new or restored scientific capabilities
of the observatory by means of a program of Early Release
Observations (EROs). In this case, the ERO program will
consist of a pair of WFPC2 observations designed to show
that Observatory science is unaffected by the SM3A "contingency"
mission.
For
reasons due primarily to contamination concerns, e.g.,
outgassing of new devices, and residual substances left
over from the servicing mission itself, these SMOV commissionings
occur over a period of weeks, and in some cases, months.
Meanwhile, various types of science operations can resume
as each corresponding science capability gets recommissioned.
The basic SMOV plan, as of this writing, is as follows:
Release
occurs early on October 21 with the V1 axis pointing into
the southern Continuous Viewing Zone (CVZ) in order to
avoid exposing the telescope optics to the sunlit portion
of the Earth. This Bright Earth Avoidance (BEA) period
lasts for 12 days, during which the PCS system is checked
out and normal attitude control is initialized.
Also
during the BEA period, the WFPC2 undergoes a decontamination
process and an initial cool-down process accompanied by
UV monitoring to verify the absence of any excess contamination
effects. Meanwhile, STIS is undergoing its engineering
initialization & check-out (incl. darks and biases).
Shortly following the completion of the 12-day BEA period,
the calibration of the new gyros is complete and the observatory
is ready to perform the EROs and to resume science operations,
using the WFPC2 and STIS CCD, in the first week of November.
In parallel with these science observations, several other
SMOV calibrations for WFPC2 and STIS will be performed.
STIS MAMAs will be recommissioned for science in the mid-November
timeframe. SMOV activities for commissioning the new FGS
will take considerably longer to complete. The FGS-2R
will be commissioned for tracking guidestars in late December,
while the last FGS SMOV activities will occur in February
of next year.
By
that time, detailed planning for SM3B and SMOV3B, currently
scheduled for December 2000, will be well underway.
FloridaToday
- October 5, 1999
Crucial
space shuttle wiring inspections continue
An
electrical short during liftoff of space shuttle Columbia
in July was traced to a wire in the payload bay with damaged
insulation. As a result of that problem, NASA decided
to inspect much of the wiring in all four shuttles and
make repairs as required. These images show technicians
examining the wires onboard orbiters Endeavour and Discovery.
The next Shuttle mission, STS-103, the third Hubble Space
Telescope Servicing Mission, is currently scheduled for
launch no earlier than Nov. 19 or 21. NASA could announce
a new shuttle launch manifest this Thursday following
a review meeting.
FloridaToday
- August 24, 1999
Hubble
mission flight hardware arrives at KSC
A
C-5 air cargo plane lands at Kennedy Space Center carrying
the payload flight hardware for the third Hubble Space
Telescope Servicing Mission (SM-3A). The equipment was
taken to KSC's Payload Hazardous Servicing Facility for
final testing and integration of payload elements. Shuttle
mission STS-103 is a "call-up" flight which is being planned
due to the need to replace portions of the Hubble's pointing
system, the gyros, which have begun to fail. Although
Hubble is operating normally and conducting its scientific
observations, only three of its six gyroscopes are working
properly. The gyroscopes allow the telescope to point
at stars, galaxies and planets. Shuttle Discovery's crew
will also replace a Fine Guidance Sensor and an older
computer with a new enhanced model, an older data tape
recorder with a solid state digital recorder, a failed
spare transmitter with a new one, and degraded insulation
on the telescope with new thermal insulation. In addition,
a Battery Voltage/Temperature Improvement Kit is slated
to be installed to protect the spacecraft batteries from
overcharging and overheating when the telescope goes into
a safe mode. Launch of STS-103 is currently targeted for
no earlier than November 19, 1999 but under review, pending
the launch date of a prior mission, STS-99, which was
delayed for wiring inspections. NASA images.
|