EVA
Day 1
Johnson
Space Center STS-103 Report # 07 Thursday, December 23,
1999, 12:30 am EST
HST Project Update - Wednesday, December
22, 11:55 pm EST
HST
Mission Update, Wednesday, December 22, 9:35 EST
HST Mission Update, Wednesday, December
22, 6:15 pm EST
Johnson Space Center STS-103 Report
# 06 Wednesday, December 22, 1999, 11:30 am EST
Space
Telescope Operations Control Center, December 22, 11:00
am, EST
HST Project Update - Wednesday, December
22, 8:30 am EST
Flight
Day 4 Images
HST
Project Update - Wednesday, December 22, 11:55 pm EST
Today's
EVA activities get an A+. The only impact on future activities
is a minor rescheduling to accommodate the remaining functional
tests for three (out of six) of the VIKs.
Here's
some additional information on the NICMOS valve opening task.
There are two coolant lines on the exterior of the NICMOS.
As they come out (from the same volume) inside the instrument,
each of these lines goes through a valve, and then terminates
in a "quick-connect bayonet", which operates much like a screw-type
garden hose connector.
These
two bayonets are how the cooler will eventually be attached
during the next servicing mission. NICMOS was installed with
caps on these bayonets to seal the lines as well as to protect
the bayonets. The valves were also closed to ensure that the
volume inside the instrument is isolated from the outside.
The astronauts' job was to remove both caps, and then open
both valves.
The desired result is to vent (to space) the volume inside
the instrument that is connected to the coolant lines. This
procedure ensures that the volume and the lines will be absolutely
free of water vapor or ice before installing the cooler.
There
were some tense moments as the astronauts reported back that
the bayonet caps did not open all the way and come off. As
they proceeded with their next task, Hubble engineers analyzed
the problem and requested that they retrieve a big wrench
from their toolbox. Using this wrench, the astronauts successfully
removed the two bayonet caps and then opened the two valves.
Johnson
Space Center STS-103 Report # 07
Thursday, December 23, 1999, 12:30 a.m. EST
Discovery
astronauts completed the two highest priority tasks of their
Hubble Space Telescope servicing Wednesday with a space walk
that was the second longest in history. Astronauts Steve Smith
and John Grunsfeld installed six new gyroscopes and six Voltage/Temperature
Improvement Kits in the telescope during their 8 hour, 15
minute spacewalk. Working deliberately, Smith and Grunsfeld
replaced three Rate Sensor Units, each containing two gyroscopes.
Four of Hubble's gyroscopes had failed, making the telescope
unable to point itself precisely enough to do science since
Nov. 13. At least three operable gyroscopes are needed to
point the telescope with the accuracy required to track its
astronomical targets.
The spacewalkers also installed Voltage/Temperature Improvement
Kits on wiring from Hubble's solar arrays to each of its six
batteries. The kits are designed to improve control of the
charging of the space telescope's 10-year-old batteries.
With
Hubble latched upright in the payload bay, Smith and Grunsfeld
completed all major tasks scheduled for the first of three
spacewalks on three consecutive days. A few minor objectives,
including applying lubricant to the door of one of the telescope's
bays and taking close-up photos of the Voltage/Temperature
Improvement Kits, were left undone. Flight and telescope controllers
decided to cancel the photography job and schedule the 10-minute
lubrication job for Thursday's space walk. The duration of
the spac ewalk was second only to the 8 hour, 29 minute space
walk from Endeavour on STS-49 in May 1992.
A
few minor problems helped account for the length of the space
walk. One of the old gyroscope-containing Rate Sensor Units
was a tight fit in the box designed to protect it on its return
to Earth, though eventually it was placed inside and the lid
closed. Another involved opening valves and removing caps
on the Near Infrared Camera and Multi-Object Spectrometer,
in preparation for restoring it to operation during the next
Hubble Servicing mission. That task too eventually was completed.
All in all flight and telescope controllers were delighted
with the accomplishments of the day. Major tasks on Thursday's
space walk by Michael Foale and Claude Nicollier include replacement
of Hubble's outmoded DF-224 computer with a more modern unit
20 times faster and with six times the memory. They also will
replace one of Hubble's three fine guidance sensors, used
to precisely point the telescope and gather scientific data.
The astronauts also may perform "get-ahead tasks," some first
scheduled for a fourth space walk. That space walk was cancelled
because of delays in Discovery's launch. Discovery remains
in excellent condition, in an orbit with a high point of 380
statute miles and a low point of 369 miles. The next status
report will be issued at 11 a.m. CST or as events warrant.
HST
Mission Update, Wednesday, December 22, 9:35 pm EST
EVA
1 is a success!
Payload
Commander Steve Smith and Mission Specialist John Grunsfeld
ventured outside Discovery today to successfully complete
the mission's first spacewalk. In tightly coordinated and
well practiced movements, they replaced all six gyros, installed
battery improvement kits and opened valves on the NICMOS science
instrument.
The six new gyros appear alive and well in preliminary tests.
Ground controllers will conduct more detailed testing tonight.
The gyros are a critical part of Hubble's pointing control
system. On November 13, 1999, the telescope ceased science
operations after the fourth of its six gyroscopes failed.
Since then, it has been in safehold while awaiting a visit
from the astronauts.
Smith
and Grunsfeld also opened valves on the Near Infrared Camera
and Multi-Object Spectrometer (NICMOS) to prepare for the
next servicing mission. In 2001, astronauts will install a
new cooling system on NICMOS to extend its life. The astronauts
also fitted Hubble's six batteries with voltage/temperature
improvement kits (VIKs) and placed protective covers on several
handrails.
Tomorrow,
spacewalkers Claude Nicollier and Mike Foale will install
Hubble's new main computer and a Fine Guidance Sensor. On
Christmas Eve, Smith and Grunsfeld will replace a transmitter,
install a digital recorder and fit Hubble with new thermal
skin.
HST
Mission Update, Wednesday, December 22, 6:15 pm EST
In
the mission's first spacewalk, astronauts Steve Smith and
John Grunsfeld successfully replaced all six gyros. Preliminary
tests show the new gyros are alive and well.
Ground
controllers will conduct more detailed testing tonight while
the astronauts sleep. Smith and Grunsfeld are now installing
improvement kits to Hubble's batteries.
HST
Project Update - Wednesday, December 22, 8:30 am EST
All
systems continue to be in excellent shape and ready to support
EVA 1 this afternoon. The crew is very eager to get to work.
Plans are being made for starting the EVA 30 minutes to an
hour ahead of schedule.
We have been taking extensive photos of Hubble's exterior
condition. A few hundred electronic pictures have already
been collected and are being analyzed. Preliminary reports
show that the exterior condition of Hubble is not much different
from when we released it in 1997.
The color printer on Discovery is working intermittently.
Johnson
Space Center STS-103 Status Report # 06
Wednesday, December 22, 1999 - 11:30 a.m. EST
With
the Hubble Space Telescope securely latched in the payload
bay, the astronauts board Discovery today will turn their
attention to the primary objective of their flight -- restoring
the capability of the 12.5-ton telescope to observe the universe.
Astronauts Steve Smith and John Grunsfeld are scheduled to
begin the first of three planned maintenance spacewalks today
at about 1:40 p.m. The crew was awakened this morning to the
song "Hucklebuck" performed by Beau Jocque and the
Zydeco Hi-Rollers, a tune that the spacewalkers heard many
times while training hundreds of hours for the mission in
the 6.5-million gallon water tank at the Johnson Space Center
in Houston.
Although not scheduled to begin until 1:40 p.m., Smith and
Grunsfeld could begin the planned six-hour spacewalk earlier
if they complete preparations ahead of schedule. Once outside
Discovery's cabin, the first task they will perform will be
to replace the telescope's three Rate Sensor Units, each of
which contains two gyroscopes. Of the six gyroscopes currently
installed in Hubble, four have failed. At least three operable
gyroscopes are needed to point the telescope with the accuracy
required to track its astronomical targets.
After the rate sensor units have been installed, the two spacewalkers
will then open valves on the telescope's Near Infrared Camera
and Multi-Object Spectrometer to purge nitrogen coolant from
that instrument in preparation for its servicing on the next
Shuttle maintenance mission. Next, they will install six Voltage/Temperature
Improvement Kits for the Hubble's batteries that will increase
the batteries' efficiency and reduce a potential for them
to overcharge and overheat. If those tasks are completed and
the spacewalkers have extra time, they may perform some additional
small jobs such as installing handrail covers and inspecting
brackets.
While Smith and Grunsfeld are outside, inside the cabin European
astronaut Jean-Francois Clervoy will control Discovery's robotic
arm, maneuvering the spacewalkers into position to work on
the telescope. Discovery's other spacewalking team, astronaut
Mike Foale and European astronaut Claude Nicollier, also will
assist from inside the cabin. Foale and Nicollier are scheduled
to perform the mission's second spacewalk tomorrow. Smith
and Grunsfeld are planned to again venture outside on Friday
for the flight's third and final spacewalk.
Discovery remains in near-perfect condition with no mechanical
problems of concern to flight controllers, as has been the
case since its launch on Sunday. It is orbiting at an altitude
of 380 by 365 statute miles. The next Mission Control Center
status report will be issued at 10 p.m. or as events warrant.
Space
Telescope Operations Control Center, Wednesday, 11:00 am,
EST
Controllers
here in the STOCC are anxiously awaiting today's first space
walk, scheduled to begin less than four hours from now.
Engineers
in the STOCC got their first up-close view of the Hubble in
almost three years last night after a flawless capture and
berthing of the Telescope by Discovery's crew.
While
the crew slept, Mission controllers in Houston guided Discovery's
payload bay cameras through a detailed survey of the Telescope
so that engineers here in the STOCC could see Hubble's condition
and compare it to the way it looked when it was last serviced
in February 1997.
Engineers
here in the STOCC report they were encouraged by what they
saw, with little apparent change to the Telescope's condition
compared to three years ago.
They
were particularly pleased to see no visible signs of peeling
paint over the areas of the Telescope currently visible -
welcome news as flecks of peeling paint could pose a contamination
risk to the Telescope's ultra-sensitive optics.
Controllers
in the STOCC completed a couple of important checks following
the berthing in Discovery's payload bay. The source for electrical
power to the Telescope was switched from Hubble's solar arrays
to the orbiter's fuel cells without a hitch, and the reconfiguration
of the communications path between the ground and Hubble was
accomplished with no significant problems.
Controllers
report they have a good data and command path to the Telescope,
critical to their ability to check out the new components
installed on Hubble by the EVA astronauts.
The
primary objective for today's EVA will be to install three
new Rate Sensor Units, each containing a pair of gyroscopes.
This will give Hubble six new gyros, needed for pointing the
telescope, and enable the Telescope to resume its scientific
mission to collect images of very faint galaxies, planets
and stars not visible from Earth.
As
soon as each Rate Sensor Unit is installed, controllers in
the STOCC will perform an "aliveness test" to check
the connection and ensure power is getting to the box. A complete
functional test of all six gyroscopes will be performed later
on today.
Another
task for Discovery's EVA astronauts today will be to install
Voltage/Temperature Improvement Kits, or VIKS, on each battery.
The batteries provide the source for the Telescope's electrical
power at night when there is no Sun. Hubble's 10-year old
batteries work well, but are more susceptible to overheating
than when they were brand new. The VIKs will prevent battery
overcharging and associated overheating.
Before
the astronauts attach the VIKs, controllers will disconnect
power to the Hubble's six batteries so there is no danger
of electrical shock to the astronauts. After the VIKs are
installed, controllers will perform an aliveness check to
test the connection, and follow that with a more comprehensive
functional test of the system later on.
Ground
systems here in the STOCC continue to perform well, and controllers
here at Goddard are ready for today's first space walk.
|