January
21, 1999
Servicing
Mission Orbital Verification Update
|
HST
Project Update
The
science program has resumed.Since SM3A, 15 GO programs have
been executed with WFPC2 and science with the STIS CCD has
been ongoing.
The
Articulated Mirror Assembly (AMA) was adjusted in the new
Fine Guidance Sensor 2R (FGS 2R) to optimize performance across
the field of view. The optical alignment activity for FGS
2R is now complete.
The
Flight Support System (FSS) and ORUC were successfully removed
from Discovery's cargo bay, and transported back to the Payload
Hazardous Servicing Facility (PHSF). Post mission deintegration
work started on the Orbital Replacement Unit (ORU) Carrier
(ORUC). The Contingency ORU Protective Enclosure (OPE), Large
OPE, Axial Science Instrument Protective Enclosure (ASIPE)
shelf and Extra-Vehicular Activity (EVA) hardware have been
removed, packed, and shipped to GSFC.
|